DCMA 14-point assessment

10. Resources and cost loading

Activities with no resource or cost.

Default threshold
None
On the demo programme
Fail0.28% (1 of 351)

Definition

Activities without resources or cost can't contribute to earned value, and give no basis for resource planning.

How the app counts it

  • Measured on incomplete activities, excluding milestones.
  • An activity passes if an assignment or the activity itself carries budgeted cost, units or at-completion cost.

Thresholds, the counting basis and whether the check counts towards the score can all be changed. See settings.

Why it matters

Earned value needs a budget on the work. Unloaded work also hides where the effort is, which makes acceleration and recovery hard to plan.

How to fix it in P6

  1. Assign resources or cost to the work that should earn value: Activity Details, Resources.
  2. Activities that carry no cost by design, such as a time risk allowance or a third party's work, will still show here. Note them rather than loading them with invented cost.