Skip to content
P6 Schedule Analytics
Analyse

Critical path and Gantt

Included in: Every paid plan, and the trial

An independent forward and backward pass in real dates. Each activity advances on its own calendar and each lag on its predecessor's, completed work is pinned to its actual dates, and the Gantt shows the result in the layout planners already read.

Gantt in P6's layout: WBS bands, actual bars to the data date, critical work in red.
Critical path and Gantt · demo programme Rev 6

What it gives you

Why recompute at all

An export carries whatever late dates were stored at the last F9. If the file wasn't rescheduled against its data date, those dates describe a plan that no longer exists. The engine detects this, recomputes float from the network, and tells you which basis it used.

The Gantt, as P6 draws it

  • Collapsible WBS tree with summary bars; ID, name, remaining duration, start, finish and total float.
  • Blue actual to the data date, green remaining, red when critical, with the planned dates as a thin bar underneath.
  • Work whose dates are already past without actuals is framed as not statused.
  • Weeks, months, quarters, years or fit, and a jump to the data date.

Check your next update before anyone else does.

Fourteen days free. Export an XER from P6 and see what it says.