Skip to content
P6 Schedule Analytics
Analyse

Earned value and earned schedule

Included in: Every paid plan, and the trial

PV, EV and AC spread across each activity's own working calendar, then SPI, CPI, EAC, TCPI and the rest. Earned Schedule gives SPI(t) and a forecast finish that stays honest late in the job, when cost-based SPI drifts back to 1.0.

Dashboard for the demo programme at its sixth update: progress, earned value and float at a glance.
Earned value and earned schedule · demo programme Rev 6

What it gives you

Read the way P6 stores it

  • Durations, lags and float are stored in hours; they're converted with each activity's own hours per day.
  • When the nominated percent-complete type is empty, the engine falls back through physical, units and duration percent.
  • With no cost in the file at all, curves and indices are shown in resource units, and labelled as such.

Measured against the programme's planned dates

Planned value is spread across each activity's planned (target) dates as the export stores them. When the export doesn't carry a separate baseline, those planned dates are the baseline, and the app states it.

Metrics and formulas as implemented
MetricFormula
BACΣ activity budget (assignment cost, else activity cost; units if no cost)
PV (BCWS)Budget × working days elapsed of the planned span, on the activity's calendar
EV (BCWP)Σ budget × % complete
AC (ACWP)Σ actual cost
SV · CVEV − PV · EV − AC
SPI · CPIEV ÷ PV · EV ÷ AC
EAC · VACBAC ÷ CPI · BAC − EAC
TCPI(BAC − EV) ÷ (BAC − AC)
ESThe date on the planned curve where today's EV would have been earned
SPI(t) · SV(t)ES ÷ AT · ES − AT, in working days
IEAC(t)Planned duration ÷ SPI(t), giving a forecast finish date

Check your next update before anyone else does.

Fourteen days free. Export an XER from P6 and see what it says.