NEC4 programme checks

Included in: Team and Enterprise plans

The programme assessed against what NEC4 ECC clause 31.2 requires it to show, the grounds for non-acceptance in 31.3, and the revised-programme requirements of 32.1 and 32.2. Each item passes, fails, doesn't apply, or is marked to check by hand with what to look for.

NEC4 compliance: clause 31 and 32 items marked pass, fail or check by hand.
NEC4 programme checks · demo programme Rev 6

What it gives you

An assessment aid, not an acceptance

Some items rely on the wording of activity names: time risk allowances, the work of the Client and Others, acceptances, access. Where nothing matches, the item is to be checked by hand, not failed, because a name search can't prove absence. Acceptance remains the Project Manager's decision.

What is assessed
ClauseItems
31.2Starting date · access dates · Key Dates · Completion Date and planned Completion · order and timing of operations · work of the Client and Others · provisions for float · time risk allowances · dates needed for access, acceptances, Client-provided Plant and Materials and information from Others · resources · health and safety (by hand) · other Scope information (by hand)
31.3Plans shown are practicable · shows the information required · represents the plans realistically · complies with the Scope (by hand)
32.1Actual progress · effect on remaining work · compensation events · delays and notified Defects · other changes to the Accepted Programme
32.2Revised programmes at the stated interval