NEC4 programme acceptance: what clause 31.3 actually asks

The four reasons a Project Manager can give for not accepting a programme, and how to check yours against them before you submit.

[FOUNDER NAME] ·

Under the NEC4 Engineering and Construction Contract the programme isn't a planning document on the side. It's how time is managed: the Accepted Programme is the baseline against which compensation events are assessed. Getting it accepted matters.

The four reasons#

Clause 31.3 gives the Project Manager four reasons for not accepting a programme:

  1. The Contractor's plans it shows are not practicable.
  2. It doesn't show the information the contract requires.
  3. It doesn't represent the Contractor's plans realistically.
  4. It doesn't comply with the Scope.

Anything else isn't a ground under clause 31.3. That's worth remembering when a programme comes back with comments.

What "the information the contract requires" means#

Clause 31.2 lists what a programme has to show. Among other things:

Some of this can be checked from the programme file. Some, such as narrative statements and health and safety provisions, can only be checked by reading.

Checking before you submit#

Most rejections are for things the programme could have shown: